Hydropol

Earthing Design and Study

Ystraffdin

SPE was contracted by Hydropol to carry out a detailed earthing design for a new 33kV hydro power station in Wales.

SPEs initial scope was to carry out a soil resistivity survey, to assess the site ground conditions, and develop the overall earthing strategy, before undertaking a detailed assessment using the CDEGS design package considering, both local and transferred faults from the WPD substation. Once the initial design and study had been carried out, SPE then produced a number of detailed earthing layout drawings.

 

 

 

Contact Us

Key Features

Client: Trant
Industry: Steam Power Generation
Plant Type: Energy From Waste
Project: Design & Protection
Contract: Lump Sum
Date: 2018-20

“SPE was appointed to provide technical design services for the HV and LV systems of the new generation plant.”