JCP Consulting Engineer / Engie

Power System Studies adn Earthing Study

Newcastle Science Park

SPE was contracted by JCP Consulting Engineers to carry out a number of power system studies for a major new development in Newcastle-Upon-Tyne.

SPE’s scope included developing a power system model of the whole system in ETAP to determine the fault levels during normal, outage and emergency conditions, and then a subsequent protection coordination study for the whole site, for phase and earth fault cases. In addition, SPE carried out a soil resistivity survey and a detailed CDEGS simulation model of the earthing system of the entire site to determine the EPR and associated touch and step voltages.

Contact Us

Key Features

Client: JCP Consulting Engineers / Engie
Industry: Building Services
Plant Type: Science Park
Project: Power System Studies
Contract: Lump Sum
Date: 2018

“SPE was appointed to undertake a fault study, protection coordination study and an earthing study for a new science park development.”